Tropical Storm Debby Sanitary Sewer Overflows

Sewer Update TW.png

There were eight spills from manhole covers at various sites throughout the city, caused by inflow and infiltration from Tropical Storm Debby. An estimated 46.6 million gallons flowed into the system from Alligator Creek alone. The corrective action with these types of spills is to use a vacuum truck, if possible, to recover as much of the spill as possible, followed by cleaning and disinfecting the area with lime.  

As required, the city made the necessary notifications about each of the spills to the Florida Department of Environmental Protection (FDEP) and the Florida Department of Emergency Management (FDEM), and crews posted notification signs at all downstream sampling locations. There are no active spills. Fines from FDEP are possible.

See the Discussion at Clearwater's Aug. 12 Work Session

Spill Locations and Details

The details of the amount and cost of each sanitary sewer overflow are as follows:

2394 Nash Street

  • Estimated total spill of 90,000 gallons with 9,000 gallons recovered via vac truck
  • Estimate $17,000 cost of labor, Vactor and lime during sanitary sewer overflow

1141 Flushing Ave.

  • Estimated total spill of 178,500 gallons with 12,000 gallons recovered
  • Estimate $19,000 cost of labor, Vactor and lime during sanitary sewer overflow

1301 Williams Drive

  • Estimated total spill of 767,250 gallons with 54,000 gallons recovered
  • Estimate $16,000 cost of labor, Vactor and lime during sanitary sewer overflow

901 Fairwood Ave.

  • Estimated total spill of 31,500 gallons with 0 gallons recovered
  • Estimate $2,000 cost of labor and lime during sanitary sewer overflow

1119 Glenmoor Court

  • Estimated total spill of 130,650 gallons with 0 gallons recovered
  • Estimate $2,000 cost of labor and lime during sanitary sewer overflow

1500 S. Belcher Road

  • Estimated total spill of 93,000 gallons with 0 gallons recovered
  • Estimate $2,000 cost of labor and lime during sanitary sewer overflow

340 Calais Lane

  • Estimated total spill of 3,480 gallons with 2,400 gallons recovered
  • Estimate $2,000 cost of labor, Vactor and lime during sanitary sewer overflow

1400 Byram Drive

  • Estimated total spill of 42,030 gallons with 7,500 gallons recovered.
  • Estimate $2,000 cost of labor, Vactor and lime during sanitary sewer overflow

 

In addition to the eight spills in the collection system, there were overflows at the East, Northeast, and Marshall Street Water Reclamation Facilities and another at Lift Station 19.

East Water Reclamation Facility (3141 Gulf to Bay Blvd.)

  • Inflows from the collection system inundated the water reclamation facility, causing approximately 5.7 million gallons of partially treated wastewater to overflow the process tanks and to flow into the stormwater system, and ultimately, Old Tampa Bay.
  • Normal flows are less than 2 MGD, but the influent flow exceed 10 MGD (MGD=million gallons per day).

Marshall Street Water Reclamation Facility (1605 Harbor Drive)

  • A Manhole overflow at the intersection of Russell Street and Holt Avenue, due to a VFD pump control failure at the Marshall Street Water Reclamation Facility.
  • An estimated 24,000 gallons of untreated wastewater overflowed and 2,400 was recovered using vac trucks.
  • Status of the issue
    • All of the Variable Frequency Drives (VFD) has been repaired
  • Preliminary cost of mitigation plan (rough estimate)
    • $4,000 to repair variable frequency drives (VFDs)
    • Estimate $2,000 cost of labor, Vactor and lime during sanitary sewer overflow

Northeast Water Reclamation Facility (3290 State Road 580)

There were two sanitary sewer overflows: Headworks and the Effluent Filters.

1. Headworks/Barscreens

  • Untreated wastewater overflowed from the headworks building (Barscreens).
  • The estimated spill volume is 63,000 Gallons with 0 recovered
  • A Duke Power outage occurred. The Headworks were not connected to the onsite generator.

2. Effluent filters

  • Due to a power failure at the Northeast WRF, effluent sand filters began overflow an estimate 5.93 million gallons of partially-treated wastewater at the clearwell and sand filter building structure. Flooding included the city’s property, the basement of the sand filter building, and reached the stormwater system that ultimately empties into Old Tampa Bay.
  • Could not start onsite generator, called Ring Power (contractor) to start it.
  • The filters were bypassed to bring back into service.

Status of the issue

  • Both spills have been stopped
  • Working to clean up spills and recover any flow that we can
  • Emptying the Reject tank and the Equalization tank
  • Spill has been abated

Impact of the issue

  • Reclaim system was taken offline through Aug. 13, when the system was restored.
  • Turbidity meter was in the basement and flooded.

Mitigation plan

  • Bypass filters to get them back in service (stopped)
  • Setting up pumps to recover what flow that we can
  • Moving the Turbidity meter out of the basement

Preliminary cost of mitigation plan (rough estimate)

  • Cost to relocate turbidimeter $5,000
  • Rental generator $42,000 per month
  • Repair of generator $10,000
  • Connect of Headworks to generator $5,000
  • Cost of Ring power to start onsite generator $5,000

Lift Station 19 (1449 Jeffords St.)

  • Failure of pump station controls resulting in overflows of 10 manholes in the upstream sewer on Jeffords Street, Hillcrest Avenue, and Barry Street.
  • Status of the issue
    • Lift station is back online, and the sanitary sewer overflows abated.
    • Lift station went offline at approximately 1 p.m. and was returned to service around 3:10 p.m. Overflowing manholes were vacuumed up to the extent possible, and lime was applied to the affected areas.
  • An estimated 50,625 gallons was released, and 3,000 gallons was recovered by vac trucks.
  • Lift station pump controls have been replaced

Reclaim Water System

All three plants bypassed tertiary treatment (sand filters) at some point. This required us to take the reclaim system offline. The system was fully returned to service Tuesday, Aug. 13.

Moving Forward 

The city and the Public Utilities Department remain committed to protecting our natural environment. The department invested roughly $35 million into the Water, Wastewater, and Reclaimed Water system in the past fiscal year and is on pace for a similar investment this year.